PGCIL commissions first leg of Raigarh-Pugalur HVDC transmission project

Implementation of the balance portion is in an advanced stage

Power Grid Corporation of India, Raigarh–Pugalur high voltage direct current transmission project, Raigarh (Chhattisgarh), Pugalur (Tamil Nadu), Power transmission lines, Independent Power Producers, HVDC technology, COVID-19 pandemic, Maharatna company

State-run Power Grid Corporation of India Ltd (PGCIL) commissioned the first leg of the 6,000 MW Raigarh–Pugalur high voltage direct current transmission project. PGCIL has commissioned Pole-1 of the Raigarh (Chhattisgarh) to Pugalur (Tamil Nadu) 1,765 km high voltage direct current (HVDC) transmission system comprising 1,500 MW capacity.

The total capacity of Raigarh-Pugalur HVDC transmission system is 6,000 MW. The work on the remaining three poles (power transmission lines) are in advance stages.

The Pole-1, the first leg of the Raigarh-Pugalur HVDC Project, between Western and Southern Region, is envisaged for evacuation of bulk power generated by Independent Power Producers (IPPs) in Chhattisgarh using HVDC technology.

This system will facilitate power flow of 1,500 MW from Western Region to Southern Region ensuring reliable and quality power supply, the statement said adding that PGCIL has completed this despite many challenges and lockdown restrictions encountered during COVID-19 pandemic.

Implementation of the balance portion of this project is in an advanced stage and will be integrated in a phased manner during FY 2020-21, the Maharatna company added.

PGCIL has been maintaining average transmission system availability above 99 per cent.

As on August 31, 2020, the total transmission assets of the PGCIL and its subsidiaries stood at 164,511 ckm ( circuit kilometres) of transmission lines, 249 sub-stations and more than 414,774 MVA of transformation capacity.

Most Popular

Awards

Olympia Group announces to build up 1.1mn sq-ft greenfield it park in Guindy
The project will have a total investment of about Rs 750 crore

Conferences

Vital pre-monsoon building works resume in Maharashtra
The state government has permitted pre-monsoon work by BMC and other agencies

Latest Issue

Sept 2020
01 Sep 2020