Sterlite Power commissions Gurgaon Palwal Transmission Project

The project will evacuate 2,000 MW to HVPNL

Sterlite Power, Gurgaon Palwal Transmission Project, Gurugram, Palwal, Haryana, Transmission system, Energy requirements of Haryana, Haryana Vidyut Prasaran Nigam, Diesel generation sets, Double circuit transmission lines, Gas insulated substations, Sohna road, Gurgaon-Manesar transmission line, Tariff-based competitive bidding, Build own operate and maintain, Vertical GIS substations, Rooftop open switchyard

Sterlite Power has announced commissioning of Gurgaon Palwal Transmission Project (GPTL) worth Rs 1,027 crore. The project will enhance the power capacity of Gurugram and Palwal areas in the state of Haryana by approximately 2,000 MW.

The project envisaged as part of the inter-state transmission system project, GPTL, will meet the peak energy requirements of Haryana, which is expected to reach more than 12,000 MW in FY20-21 from 9,000 MW in FY14-15.

The project will evacuate approximately 2,000 MW to Haryana Vidyut Prasaran Nigam (HVPNL) ensuring access to reliable power for more than three million households in the state. With more than 10,000 high capacity diesel generation (DG) sets installed in Gurugram, the project will play a pivotal role in minimising their usage and subsequent reduction in pollution levels brought on by combustion of diesel.

The project consists of four 400 kV double circuit transmission lines with total length of 143 km, three gas insulated substations (GIS) at Prithla, Kadarpur and Sohna road, two bay extensions at Dhanonda and a LILO connecting the 400 kVDC Gurgaon-Manesar transmission line. The company had secured the project through tariff-based competitive bidding process and executed it under the build, own, operate and maintain (BOOM) model.

The project implemented one-of-its-kind innovations with India’s first vertical GIS substations being built at Prithla, Kadarpur and Sohna. The 400/220 kV GIS substations are multi-storey substations with a rooftop 220 kV open switchyard.

A conventional GIS substation of similar capacity generally requires 12 acres of land, but the solution is built on 3.8 acre resulting in 75% reduction in land size. Apart from the vertical substations, multi-circuit monopole towers have been built to optimise the space challenges related to the project.

Most Popular

Awards

Olympia Group announces to build up 1.1mn sq-ft greenfield it park in Guindy
The project will have a total investment of about Rs 750 crore

Conferences

Vital pre-monsoon building works resume in Maharashtra
The state government has permitted pre-monsoon work by BMC and other agencies

Latest Issue

Sept 2020
01 Sep 2020