Coal India chalks out strategy to meet 660 million tonne production target for FY20

Coal offtake was at 410 MT till December 27, 2019 as against a target of 467 MT

Coal India, Coal production, Mahanadi Coalfields, South Eastern Coalfields, Coal mining

Amid concerns that Coal India may fall short of its 660 million tonne (MT) production target for the current fiscal, the miner has planned to ramp up daily output to meet the goal, officials said. Till December, the miner is expected to produce close to 390 MT of coal and will require another 270 MT in the last quarter of this fiscal to meet the annual production target.

Currently, Coal India produces 1.8 MT per day while the asking rate to achieve the target is 2.9 MT. Internally, Coal India has planned to raise its production to 3 MT per day at least in February and March next year to inch closer to the target. According to the provisional data, the miner produced 330.38 MT of coal during April-November in the 2019-20 fiscal, down by 7.8 per cent from 358.30 MT in the year-ago period.

Unless the miner increases its daily production to 2.5 MT per day from January to March period, it will struggle to surpass the production figure of the last fiscal. In 2018-19, Coal India produced 606.89 MT while dispatch was at 608.14 MT. Coal India's offtake at 363.63 MT during April- November period was down by 7.2 per cent from 392.02 MT supplied in the year-ago period.

Coal offtake was at 410 MT till December 27, 2019 as against a target of 467 MT. In October, a rating agency had projected that the coal behemoth might miss the production target by 50-75 MT in the current fiscal.

Performance of Coal India's two key subsidiaries- Mahanadi Coalfields Ltd (MCL) and South Eastern Coalfields Ltd (SECL)- will be crucial in remaining three months of the current fiscal to meet its production target. Mining activities in the two subsidiaries had been hit severely during monsoon and also due to law and order issues.

According to production data, SECL and MCL registered a negative growth of 14.5% and 9.8% respectively as on December 27, 2019, and these companies have been taking all measures to overcome hurdles and ramp up production. CIL, however, is apprehensive about coal demand with declining electricity generation of thermal power plants in the country till November this year, officials said.

"If the current trend continues, it have an adverse impact on CIL's production and dispatch," they added.

Most Popular

Awards

Olympia Group announces to build up 1.1mn sq-ft greenfield it park in Guindy
The project will have a total investment of about Rs 750 crore

Conferences

Vital pre-monsoon building works resume in Maharashtra
The state government has permitted pre-monsoon work by BMC and other agencies

Latest Issue

June 2020
10 Jun 2020